Interlagos - Sector
Business model
Performance contract
Object
This project was conducted in two phases/two contracts, in which Vitalux was hired through a bidding process by Sabesp to implement a Loss Reduction program, via a Performance Contract, in areas of high social vulnerability, using water and sewage regularization actions with the suppression of irregular infrastructure and recovery of clients, covering the Interlagos supply sector.
Scope
- Execution of New Water Connections (TL0)
- Executions of New Water and Sewage connections (TL1)
- Regularization of connections that were inactive and with zero consumption
- Actions for raising awareness and interventions on low-income communities.
Benefits
Reduction in Water Losses = 535,000 m³/year
|
Indicators
Water available to 3,300 households | |
Prevented CO2 emissions = |