ABC WWTP

Business model

Hybrid Contract: Performance + PEE

logotipo home vitalux 8  ENELlogo aneel pee

Object

Through a Public Call for Projects, Sabesp structured a Project for the Final Sewage Pumping ABC WWTP, with a total investment of R$ 4.84 MM, being part of the resources by the ENEL SP Program (R$ 0.83 MM) and another share as a compensation by Sabesp (R$ 4.01 MM). ​

Vitalux was hired through a bidding process by Sabesp, covering the whole administration of the Energy Efficiency Program and with the responsibility of the compensation in the Performance format.

Scope

Substitution of 01 motor pump set (800 kW/1.100 CV)​

Installation of a new transformer and electric power panels, with frequency inverter​.

Benefits
Cases RaioVerde
Energy Saved = 1,860 MWh/year
Cases DinheiroVerde Financial Economy = R$ 715,000/year
Indicators

Cases CasaEnergiaVerde Energy available to 970 households
Cases CO2Verde Prevented CO2 emissions = 180 tons/year